End of Warranty inspection for the entire electrical infrastructure of the 50MW Wind Power Plant at Gul Ahmed Energy Limited. This comprehensive assessment aimed to ensure that all components and systems were functioning as per the specified parameters. The inspection encompassed testing of various grid equipment, including power transformers, circuit breakers, auxiliary transformers, disconnectors, surge arrestors, current transformers (CTs), potential transformers (PTs), medium voltage (MV) panels, protection relays, and battery banks.
The tests included WRT, C & DF, TTR, IR and oil testing of Power transformers, contact resistance and timing tests of circuit breakers and MV panels. Surge tests of surge arresters and WRT, IR and Polarity tests of CT and VT/CCVT. Partial discharge tests, Relay tests, Thermal Imaging and Earthing tests were also performed.
Previous slide
Next slide
Previous slide
Next slide
Technical Engineering Services.
MASTER GREEN ENERGY WIND POWER PLANT, JHIMPIR
The end-of-warranty inspection covered the entire electrical infrastructure of the 50 MW Wind Power Plant at Master Green Power Plant Limited. This thorough evaluation aimed to verify that all components and systems were operating within specified parameters. The inspection involved testing various grid equipment such as power transformers, circuit breakers, auxiliary transformers, disconnectors, surge arrestors, current transformers (CTs), potential transformers (PTs), medium voltage (MV) panels, protection relays, and battery banks.
The tests included winding resistance tests (WRT), transformer turns ratio (TTR), insulation resistance (IR), capacitance and dissipation factor (C & DF) and oil testing for power transformers. For circuit breakers and MV panels, tests encompassed contact resistance and timing. Surge tests were conducted for surge arresters, while CTs and PTs underwent WRT, IR, and polarity tests, along with voltage transformer/capacitor voltage transformer (VT/CCVT) assessments. Relay testing, thermal imaging, earthing tests, partial discharge tests and battery load tests were also performed.
Technical Engineering Services.
TRICOM WIND POWER PLANT, JHIMPIR
The end-of-warranty inspection encompassed the entirety of the electrical infrastructure at Tricom Wind’s 50 MW Wind Power Plant. This thorough examination was conducted to ensure that all elements and systems were functioning within designated parameters. Various grid equipment underwent testing, including power transformers, circuit breakers, auxiliary transformers, disconnectors, surge arrestors, current transformers (CTs), potential transformers (PTs), medium voltage (MV) panels, protection relays, and battery banks.
Testing procedures involved a range of assessments, such as winding resistance tests (WRT), transformer turns ratio (TTR), insulation resistance (IR), capacitance and dissipation factor (C & DF) and oil testing for power transformers. Circuit breakers and MV panels were subjected to contact resistance and timing tests. Surge tests were carried out for surge arresters, and CTs and PTs underwent WRT, IR, and polarity examinations, along with evaluations of voltage transformer/capacitor voltage transformer (VT/CCVT) setups. Additionally, relay testing, thermal imaging, earthing assessments, partial discharge tests, and battery load tests were conducted.
Previous slide
Next slide
Previous slide
Next slide
Technical Engineering Services.
INDUS WIND POWER PLANT, JHIMPIR
The end-of-warranty inspection covered the entire electrical infrastructure of the 50 MW Wind Power Plant at Indus Wind Power Plant Limited. This thorough evaluation aimed to verify that all components and systems were operating within specified parameters. The inspection involved testing various grid equipment such as power transformers, circuit breakers, disconnectors, surge arrestors, current transformers (CTs), potential transformers (PTs), medium voltage (MV) panels, protection relays, and battery banks.
The tests included winding resistance tests (WRT), transformer turns ratio (TTR), insulation resistance (IR), capacitance and dissipation factor (C & DF) and oil testing for power transformers. For circuit breakers and MV panels, tests encompassed contact resistance and timing. Surge tests were conducted for surge arresters, while CTs and PTs underwent WRT, IR, and polarity tests, along with voltage transformer(VT/CCVT). Relay testing, thermal imaging, earthing tests, partial discharge tests and battery load tests were also performed.
Technical Engineering Services.
METRO WIND POWER PLANT, JHIMPIR
The end-of-warranty inspection encompassed the entirety of the electrical infrastructure at Metro Wind’s 50 MW Wind Power Plant. This thorough examination was conducted to ensure that all elements and systems were functioning within designated parameters. Various grid equipment underwent testing, including power transformers, circuit breakers, auxiliary transformers, disconnectors, surge arrestors, current transformers (CTs), potential transformers (PTs), medium voltage (MV) panels, protection relays, and battery banks.
Testing procedures involved a range of assessments, such as winding resistance tests (WRT), transformer turns ratio (TTR), insulation resistance (IR), capacitance and dissipation factor (C & DF) and oil testing for power transformers. Circuit breakers and MV panels were subjected to contact resistance and timing tests. Surge tests were carried out for surge arresters, and CTs and PTs underwent WRT, IR, and polarity examinations, along with evaluations of voltage transformer/capacitor voltage transformer (VT/CCVT) setups. Additionally, relay testing, thermal imaging, earthing assessments, partial discharge tests, and battery load tests were conducted.
Previous slide
Next slide
Previous slide
Next slide
Technical Engineering Services.
INDUS WIND POWER PLANT, JHIMPIR
The end-of-warranty inspection covered the entire electrical infrastructure of the 50 MW Wind Power Plant at Indus Wind Power Plant Limited. This thorough evaluation aimed to verify that all components and systems were operating within specified parameters. The inspection involved testing various grid equipment such as power transformers, circuit breakers, disconnectors, surge arrestors, current transformers (CTs), potential transformers (PTs), medium voltage (MV) panels, protection relays, and battery banks.
The tests included winding resistance tests (WRT), transformer turns ratio (TTR), insulation resistance (IR), capacitance and dissipation factor (C & DF) and oil testing for power transformers. For circuit breakers and MV panels, tests encompassed contact resistance and timing. Surge tests were conducted for surge arresters, while CTs and PTs underwent WRT, IR, and polarity tests, along with voltage transformer(VT/CCVT). Relay testing, thermal imaging, earthing tests, partial discharge tests and battery load tests were also performed.
Technical Engineering Services.
LIBERTY 2 WIND POWER PLANT, JHIMPIR
The end-of-warranty inspection covered the entire electrical infrastructure of the 50 MW Wind Power Plant at Liberty 2 Wind Power Plant Limited. This thorough evaluation aimed to verify that all components and systems were operating within specified parameters. The inspection involved testing various grid equipment such as power transformers, circuit breakers, auxiliary transformers, disconnectors, surge arrestors, current transformers (CTs), potential transformers (PTs), medium voltage (MV) panels, protection relays, and battery banks.
The tests included winding resistance tests (WRT), transformer turns ratio (TTR), insulation resistance (IR), capacitance and dissipation factor (C & DF) and oil testing for power transformers. For circuit breakers and MV panels, tests encompassed contact resistance and timing. Surge tests were conducted for surge arresters, while CTs and PTs underwent WRT, IR, and polarity tests, along with voltage transformer/capacitor voltage transformer (VT/CCVT) assessments. Relay testing, thermal imaging, earthing tests, partial discharge tests and battery load tests were also performed. Relay testing, thermal imaging, earthing tests and battery load tests were also performed.
Previous slide
Next slide
Technical Engineering Services.
PAK OASIS (PVT) LTD
Testing and Commissioning of Substation (R.O Plant) South region Karachi.Test Performed:
Protection Relay Test Open Circuit, Short circuit, E/F, Current Transformer & Potential Transformer ratio test, heaters, control circuitry Test for MV switchgear.
Transformer Turn Ratio Test, Insulation Resistance Test for Distribution Transformer up to 1500 KVA, Make: Siemens.
Insulation Resistance Test, operation mechanism for MCCB, for LV Distribution panel. Testing, commissioning of PFI Relay.
Technical Engineering Services.
ALSTOM GRID PAKISTAN PRIVATE (LTD)
Testing and Commissioning Projects
Project Description:
Testing of 220 KV/11KV Transformer, Test Performed; C & DF, TTR, WR and IR Test.
Testing and Commissioning of 12 MW WHRS at Attock Cement Pakistan.
Testing and Commissioning of PLC Panels at Attock Cement Pakistan.
Testing and Commissioning of 2000 KVA Transformer at Attock Cement Pakistan.
Testing and Commissioning of MV Panel at SSGC.
Previous slide
Next slide
Previous slide
Next slide
Technical Engineering Services.
INDUS MOTOR COMPANY (IMC)
Technical Engineering Services providing services of electrical instrumentation and Mechanical Fabrication in various department i.e. Co- Generation, Paint shop, Bumper shop, Weld shop, Assembly, Training Center etc.
Project:
Installation, testing & commissioning of LV panels and installation of Bus Tie Duct.
Installation, testing & commissioning of Power Transformers 1200 KVA, 1000 KVA and 3000 KVA for various departments.
Underground Cable Testing of 11 KV through cable fault detector and repairing/jointing of H.T cable and termination. Fabrication and installation of Primer Tank and sludge Tank at bumper shop.
Supply and installation of sequence tanning board for Training Center.
Maintenance of L.V panels at (CO-GENERATION) Power Plant.
Complete Electrification of DC Shunt and panel for Primer Tank.
Complete Earthing System of Cogeneration Power Plant.
Supply and Modification of Boiler electrical instruments and controlling through Microcontroller, transmitters, thermocouple and slow opening valve at Bumper shop. Design, Supply and installation of part booth burner control panel at Paint shop.